Billing rates and project budgets

Modified on Tue, 24 Nov at 8:42 AM

For: Managers  ·  Time: about 5 minutes

You need: a project and access to the Billing tab

Add rates and a budget to a project to see what it's costing and how much budget is left, using both scheduled and reported time.

Set a project budget

  1. Open the project: click its name in the sidebar and use the pencil icon, or right-click one of its bookings and choose ⋮ → Edit Project.
  2. Open the Billing tab.
  3. Under Budget, choose a category, the currency, and enter an amount, hours or days. Hours and days convert automatically.
  4. Click add budget category to split the budget, for example Design and Build, so each draws down separately.
  5. Tick Non-billable Project if the work isn't charged to a client. Its spend then won't count in billable reports.

Set rates

  • External Project Rates are what you charge. Pick an External Project Hourly Rate from your rate list, or click Add new rate. It applies to everyone on the project without their own rate.
  • Custom external Resources Rates override the project rate for specific people on this project only.
  • Internal Project Rates are your cost. Comparing external and internal rates shows your margin.
  • Each person can also have default rates on the Rates tab of their resource window.

Add fixed costs

On the Fixed cost tab, click add new fixed cost for one-off costs such as materials or licences. Tick the option to subtract them from the project budget. Click Update to save.

Setting a budget, a rate and a fixed cost

Setting a budget, a rate and a fixed cost

See spend against budget

  • On the scheduler, open the project and use the Financials panel to see scheduled and reported time, spend at external and internal rates, and remaining budget.
  • In Reports, build a project report with budget, burn and spend columns.

? Tip: Rates are kept with their start dates, so adding a new rate when prices change won't rewrite the history of past work.

ℹ️ Note: Billing rates and budgets may depend on your plan. Check with your account manager if you can't see the Billing tab.

Related articles

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article