Import projects, resources and bookings

Modified on Tue, 24 Nov at 8:43 AM

For: Admins  ·  Time: about 20 minutes

You need: admin access and your data in CSV or Excel

Moving from spreadsheets or another tool? Import your data in this order: resources, then projects, then bookings, because bookings need the people and projects to exist first.

1. Import resources

Go to Settings → Manage → Manage Resources → Add multiple. Paste or upload a CSV with First name, Last name and Email. See Add and invite resources in bulk (CSV).

2. Import projects

  1. Go to Settings → Manage → Manage Projects → Add Multiple Projects. You can also use Add new → ⋮ next to New project → Bulk Add Projects in the scheduler sidebar.
  2. Paste comma-separated data (one project per line) or upload a .csv or Excel file. A template is available to download.
  3. Click Continue, match each column to a field, then click Import.
ColumnNotes
NameRequired and must be unique
Project CodeUsed to update an existing project instead of creating a new one
GroupAn existing or new project group; new groups are created for you
Statusactive (default), archived, pending, planned or floating
BudgetHours or cash, with the matching budget field
Default RateTRUE uses your account rate; FALSE lets you set a custom one
Start / EndDates as YYYY-MM-DD
Note, Links 1–5Optional notes and links
Sunday–SaturdayTRUE or FALSE for working days; blank uses your account defaults

3. Import bookings

  1. Go to Settings → Manage Projects → Add Bookings and click Download CSV Template.
  2. Click Upload Multiple Bookings, then Download All Resources and Download All Projects to get the IDs you'll need.
  3. Fill in one row per booking (columns below).
  4. Upload the file.
ColumnNotes
event_idLeave blank for a new booking, or enter an ID to update one
event_start / event_endDates as mm/dd/yyyy
event_resourceThe resource ID
event_projectThe project ID
event_stateHOURS_DAY, TOTAL_HOURS or PERCENTAGE
event_state_valueMinutes per day, total minutes, or the percentage. Blank means a full day
event_noteOptional note

Importing projects and bookings from CSV

Importing projects and bookings from CSV

⚠️ Warning: Check the dates' format carefully: projects use YYYY-MM-DD and bookings use mm/dd/yyyy.

? Tip: To change lots of existing bookings at once, use Download All Bookings, edit the rows (keeping each event_id) and upload them again.

ℹ️ Note: For large migrations, ask your account manager. Our team can help import your data.

Related articles

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article